Thursday, September 9, 2010

Josh A Shift 09/09/2010

Hello All,

They finally released some funds to order parts to repair one of the two grinders we still have tore down.  I chose the bigger one and ordered the parts for it today.  I’ll order the parts to repair the little Solo grinder next month.

Also, I’m got approval to do a CER tomorrow for two New Grinders specified for Pelethane (Santoprene).  I chose to go with AEC because they have recently purchased Cumberland and Nelmor which are both good brands.  I sent them a box of our runners to heat up and do grinding trials on.  Rapid makes a good grinder, but I just guess the cheap ones Hank bought have left a bad taste in my mouth.

Attached are the specs and quote so that everyone can check it out.

 

Thanks

 

  Joshua Ledbetter

  Molding Maintenance Manager

  Manufacturing Engineer

  Oreck Manufacturing Company

  931-239-3235

 

Mike Daniels-B Shift

Good morning, 

                       

 I helped Gary replace dump cylinder on pump#1 on mezz. It was sticking at start of shift. Went ahead and replaced the cylinders on pumps #2,3,4 and 5(per josh) found that the flange on pump 3 was cracked bad. I called Josh to see if we had a replacement,(we didn’t) so I tig welded it back together and Josh and I put it back together. Probably down 2hrs. Other than that fairly peaceful night in molding.

 

Have a great day.

Tuesday, September 7, 2010

Ronnie Upchurch

MP-20  Nozzle adapter heater band was bad---- replaced.

 

MP-25  The cores were backwards.  Normally the core cylinder is fixed & the shaft moves ;  on the hokey handle mold the cylinder moves , so the

            set & pull lines hook up backwards.

 

MP-25  Replaced the motor overload on the grinder.

 

MP-2  The rear zone heater - mercury contactor blew up. Mark & I  contacted Walter Marcum. We cleaned out the cabinet & disposed of the mercury

          In the drum in the recycle room. Installed a new contactor.