MP25 adjusted the part verify switch
Worked on PMs
Overall good night
MP20 Replaced the ejector cylinder, end cap, piston rings, and seals.
MP-25 Installed a relay on the robot up stroke; to prevent the cycle from stopping when the grippers drop the sprue.
MP-5 Core 2 not reading pull. The switch on the bottom cylinder wasn’t making.
MP-19 Ordered a seal kit for the sled cylinder.
1/29/2011
MP-11 Replaced missing switch levers on control panel.
MP-10 Added two more quick connects on air manifold. One 3/8” & one ½”.
D-32 on mezzanine wouldn’t restart—Bad process blower contactor—out of stock. I was going to swap with D26, but the process blower motor was locked up
& had two blown fuses. I put a 100# per hour dryer in to get by---- no spare 200# .Had to wait till Sunday to pull the two dryers down & take to the shop
to repair – “ No Overtime”
1/30/2011
D-32 Need to order a contactor for this one. Old one is on desk.
D-26 I replaced the process blower unit.
MP-13 The ejector lost it position. I found the collar that the transducer read position from had fallen off. Re installed.
I am leaving early today, because I stayed over an hour last night.