MP#17- They set that mold that needed to run with cores tonight, then pulled it out after I told them it could not run in there yet.
Do we need to wire in air eject or cores for this machine?
I was not certain as to what was decided as far as that goes, but I thought that Josh was going to have them install air cylinders on the tool.
Please let me know what we need to do so as not to attempt any rigging unauthorized!
What are we going to tie into? Air? Core 1? etc. Need a control switch installed? Is there outputs assigned? Software ready for it?
Roger put me on the spot with it and I wasn't really sure what to tell him so give me a call later or talk to Ronnie today so I can pick up where he leaves off today. Thanks.
Also got the cav 2 gate cutter disassembled, the intake test fixture disassembled, the air ten gate cutter stell table stripped down, and the welder table disassembled and palletized.
Saved the opto switches for the fan hsg assy project and plc from intake tester.
Sean
Saturday, November 19, 2011
Wednesday, November 16, 2011
11.15.11- Sean
Mp#20- Put on a nozzle heater band.
Mp#1- They set a mold in the press that was too short for the daylight again. Roger requested that I make up some spacer bars to bolt onto the moving platen so it could be installed.
I drilled and marked them with "Caution" and put threaded 1/2" holes on top so they could be moved with lifting rings or eye bolts.
It was late before he got it set so I was only able to clean the outside of the press and around it .
I noticed the lube oil line is broken on the non-operator side skate and I could not locate any fittings with ferules for that tubing.
I did replace the grease tube and noticed that we are running very low on that grease, especially now that we have 2 presses, we should order some more for them.
Mp#10- replaced missing screws from the nut feeder tracks and unstuck a screw that had found its way into it.
Have a nice day.
Sean
Mp#1- They set a mold in the press that was too short for the daylight again. Roger requested that I make up some spacer bars to bolt onto the moving platen so it could be installed.
I drilled and marked them with "Caution" and put threaded 1/2" holes on top so they could be moved with lifting rings or eye bolts.
It was late before he got it set so I was only able to clean the outside of the press and around it .
I noticed the lube oil line is broken on the non-operator side skate and I could not locate any fittings with ferules for that tubing.
I did replace the grease tube and noticed that we are running very low on that grease, especially now that we have 2 presses, we should order some more for them.
Mp#10- replaced missing screws from the nut feeder tracks and unstuck a screw that had found its way into it.