Thursday, December 9, 2010

Ronnie Upchurch

                   12/08/10

 

Worked on fascia hot stamp.

 

MP-13  Pulled barrel cover & cleaned off blow back – ¾ down the barrel. I was able to save heater band wiring & the covers , with some minor body work.

 

MP-19 The DME t.c. was reading low , but the mold heater was running away. I found that the t,c, wire had been pinched behind the mold clamp. Replaced.

 

 

                   12/09/10

 

MP-13  Pulled  the Conair heater to get the part #. There were two possible numbers for that model.  I ordered replacements .  There are only two heaters

       Per zone – 240 v.

 

MP-10   We cleaned out the nut feeder , Again , & cleaned a box of nuts. Mark adjusted the tracks.

 

MP-26  The center knock-out mounting stud on the eject. plate fell off.  Reinstalled.

 

I ordered a new adjustment screw & nut for MP-24 spacer adjustment.

 

I sent the top cover drill out for repair.

 

I ordered a new replacement motor for the small Solo grinder.