R2 FACIA PROJECT

We are about to begin the new R2 Facia project which will involve 7 or 8 new part numbers for molding, these will be run on MP22.  A new station will be constructed with a shuttle mechanism to present individually formed labels using two nests (operator loaded) on a subplate that mimic the mold. Gary will head up the physical building (construction, tooling) of this station, but may ask any of us to help out as needed to complete in a timely manner.  Sean will work with me on the electrical.  If anyone signs out components for this project in MRO, please sign out to R2 Facia.

 

The new Star robot for MP26 should arrive anytime.  A robot interface will need to be installed and the top of the machine will need to be drilled and tapped.  I would like Mike to install the hole pattern for the robot on the top of the machine.

 

Ronnie is ordering parts for the Conair dryer in the shop.

 

Parts are on order for the Interroll Decline Conveyor in shop.

 

Branson came in on the welder for the Ultimate Canister Vacuum Inlet Assembly, the setting are as follows:

Weld Time         .350

Hold                  .5

Trigger              3.5

Air Pressure      25psi

AB                    OFF

Stroke               3.5 inches

Adjustable Leveling plate is level.

 

Parts should be here anytime for the new Pilot Destruction Mechanism.  This may replace the duck bill style.

 

 

 

Mark McKee

Technical Specialist

Oreck Manufacturing Company

1400 Salem Rd

CookevilleTN  38506

mmckee@oreck.com

PH      931.646.7856

CELL  931.644.5289

FAX    931.646.7615

 