Mp#26- Installed the box with SPI base and routed the cable for the sprue picker interface. Will Continue interfacing it in on Monday. DR#11- replaced the process heat contactor. Moved some of the equipment out of the shop that has been waiting on parts. Tagged the items with signs. Including the Hot Stamp press Randy Russell was working on. Cleaned up in shop to make room for the R2 Fascia IML project. Continued with PM's. Have a great weekend. Call if there is anything I can help with! Sean