Mp#10- parts were not welding the deflector. Double checked the process before i began working on it. It was running at 56 seconds cycle time. Water was partailly shut off, but not all the way. To cut it short, Marty and I adjusted the fixture and just kept working with it until they were welding good again.
Worked on the 900 Yushin sprue picker. I wired up the other interface box using the 200vac transformer because the print was calling for that circuit box. It came up but indicated E-stop faults which were from a blown fuse. Changed fuse out, got it up to a "kick cyclinder input error" .
It probably has a short in either the sensor or the pendant because it keeps blowing the fuse. If it turns out to be the pendant then I can still change out the board/pendant with one of the others.
Mp#2- I attempted to plumb in the hydraulics on Core #2 . The pressure line is tapped into MX2 feeding off P1/P3 circuit. It has NOT been checked yet, still need to turn on the Core 2 convecs/ options etc. and set up pressures and flow controls etc. I have some questions for Josh about this when I come in next or can call me, etc.
Went through the trailor and tried to straighten up etc. Moved the 3 small conveyors into the shop and let the process techs know that they can use them to draw runners out from under presses where needed. No takers yet.
The Pump motor on #3 is limping along for now. I understand that Josh is checking on getting it rewound, etc.
Call if i am needed. Next week is my short week and will be glad to come in and assist at short notice. Thanks.
Sean