2/25/11
Worked on the “Randy Russell” hot stamp project.
Ordered a large assortment set of metric o-rings from IR-G.
MP-13 Started getting material together to replace the section between the hopper & feed throat that keeps clogging up.
MP-6&7 Vacuumed out oil pans & emptied the oil vac.
2/26/11
MP-13 Made a new adapter plate for the hopper & remounted.
MP-24 Fabricated a temporary knock-off tool on the eoat for the wheel mold.
MP-16 Replaced the timer relay in thermolater – T-4.
2/27/11
MP-2 Core 2 pull not making. The switch wasn’t working, but when I removed it from the cylinder, it checked OK. I changed it out. Working OK.
MP-6 I got the numbers off the pump to order a pump seal.
MP-15 Need to order a PS1 pressure switch. It build tonnage -2000psi- but bleeds off to about 1650psi.
MP-5 The nozzle heat wasn’t consistent. The contactor coil was weak. Replaced.
MP-2 The male quick connect on core 1 was leaking. Removed, put on Teflon tape, & reinstalled.