Friday, April 1, 2011
3.31.11 D-shift Sean
Thursday, March 31, 2011
R2 FACIA PROJECT
We are about to begin the new R2 Facia project which will involve 7 or 8 new part numbers for molding, these will be run on MP22. A new station will be constructed with a shuttle mechanism to present individually formed labels using two nests (operator loaded) on a subplate that mimic the mold.
The new Star robot for MP26 should arrive anytime. A robot interface will need to be installed and the top of the machine will need to be drilled and tapped. I would like Mike to install the hole pattern for the robot on the top of the machine.
Ronnie is ordering parts for the Conair dryer in the shop.
Parts are on order for the Interroll Decline Conveyor in shop.
Branson came in on the welder for the Ultimate Canister Vacuum Inlet Assembly, the setting are as follows:
Weld Time .350
Hold .5
Trigger 3.5
Air Pressure 25psi
AB OFF
Stroke 3.5 inches
Adjustable Leveling plate is level.
Parts should be here anytime for the new Pilot Destruction Mechanism. This may replace the duck bill style.
Mark McKee
Technical Specialist
Oreck Manufacturing Company
mmckee@oreck.com
PH 931.646.7856
CELL 931.644.5289
FAX 931.646.7615
Wednesday, March 30, 2011
Ronnie Upchurch
MP-25 Had to unwire the relay & gripper so they could use the “B” side eoat. The input must be bad; it’s staying made.
MP-2 Core set wouldn’t work. I found some cut wires.
DR-29 Novatec – I changed the desiccant. It was discolored & contaminated.
MP-6 Vacuumed oil pan.
Monday, March 28, 2011
Parts
Gentlemen,
FYI
Conair 1250W regen heaters are on order, ½-13 all thread is a stock item in MRO and is located in the extrusion rack.
Mark McKee
Technical Specialist
Oreck Manufacturing Company
mmckee@oreck.com
PH 931.646.7856
CELL 931.644.5289
FAX 931.646.7615
3.27.11 Weekend D-shift Sean
Sunday, March 27, 2011
Ronnie Upchurch
MP-18 The machine disconnect & switch gear came apart. I turned the power on so they could do a mold change. The E-stop button on the control panel
fell off, I reinstalled it.
DR-11 Mezzanine – Process alarm. I found the rotation backwards. Rewired.
DR-6 Mezzanine – Temp. wasn’t coming up. I found the bed motor drive gear had slipped down on the shaft & wasn’t contacting the bed gear. Readjusted.
MP-4 Had a small blowback. Had to replace the T.C. wire
MP-18 Had to replace the safety docking switch on the grinder.
MP-9 Replaced the robot conveyor relay.
MP-25 I don’t know why the relay isn’t bypassing the gripper switch. When they shut it down we’ll be able to tear into it.
Saturday, March 26, 2011
Ronnie Upchurch
MP-24 Installed a relay to give a gripper signal when the arm is in the up position. MP-22 & 25 already have a relay.
I worked with Tony Cannon & Doug Mason setting up the Branson welder for the vacuum inlet assembly.
We got in eight different sizes of rubber plugs to use on hydraulic lines & valves. I put them under the hose crimp bench.
MP-10 is to stay down all weekend. The nut press fixture has to be changed to work with the engineering change made to the part. Mark & Gary will
finish it on Monday.
Thursday, March 24, 2011
3.23.11 B-shift Sean
I ran it on the robot for 2 hours and then shut it down because Marty did not have an operator for it. I posted a note on the door to let techs know that it has had the pump rebuilt and system pressures may be different than before.
Robot on #25 needs a new runner gripper sensor. We could not use it because it is reading "on" all the time and alarming LS4S alarm the robot when you put it into auto. I checked it out and found the wires had pulled back into the conduit and may have shorted. I tried to leave them disconnected but the alarm still would not clear. So I borrowed the sensor from #24 and it did not work either. May have a problem with the board. I left it disconnected until we get a new sensor. The wiring will need to be double checked before installing the sensor.
The robot works, just not the sprue grip arm because of the sensor alarm LS4S.
Have a great day,
Sean
Wednesday, March 23, 2011
3.22.11 D-shift Sean
Mp#21- Hooked up the ASL filtration cart and let it run on it for a month. Try to watch that the pressure gage does not go over 35. If it does, we will need to backflush it. Procedure for that is on the cart. We can move it around every month to each of the presses we think may need it.
Continued with PM's.
Have a great day.
Sean
Tuesday, March 22, 2011
Ronnie Upchurch
MP-21 Got info from Toshiba tech. to check pump pressure – Press is ready to run.
MP-4 Replaced two hydraulic hoses & adjusted the angle of the fittings to keep the hoses off the deck.
Wiring cores & eject. switches on new molds.
Ronnie Upchurch
MP-12 They had some more trouble with the injection encoder rail gear. I found a new gear in the L-1 cabinet. Mark installed it. I put some grease on the extruder
follower arm – it was squealin ! I’ll order some more of the rail gears.
MP-24 I hooked up an eject. back safety switch.
MP-21 I drained the oil tank & pulled the tank inlet strainers. They were both 90% clogged. I cleaned them in the parts washer & reinstalled. Josh wants to run
the static filter on it for awhile; because there’s still some sediment in the bottom. I cleaned out what I could reach with the oil vac.
MP-25 Cinn. Milacron dryer kept going into high temp. alarm. First I thought it was the mercury contactor sticking. It turned out to be a loose connection – the
process temp. probe at the board.
3.21.11 D-shift Sean
Mp#22- IML was running and the "low Label" light was staying on. He thought it was a sensor but it just turned out to be low of labels.
Mp#8- The operator they call "The Crow" fell asleep on the fans and crashed the robot. I have a picture for you.

Continued with PM's.
Have a good day.
Sean
Monday, March 21, 2011
Ronnie Upchurch
MP-21 Mark & I installed the pump. I started it up & it ran quiet, but after a short time, it started heating up & it is still pumping air into the tank. I believe the
tank inlet screen is stopped up & the only way to get to it is to drain the tank. I locked it out again & we can get back on it Monday.
I helped Henry get the new molds off the truck. The three smaller molds had fallen off the pallet – no damage – just a pain to get to.
3-20-11 B shift
Mp12 the strip gear on injection position sensor broke not sure how. Its just glued on so I cleaned reglued so if you have issues with screw position check this first.
Worked on PMs
Mike Daniels
Technical Specialist
Oreck Manufacturing
Cell 931.287.6252
Eat. Sleep. Fish.
Thursday, March 17, 2011
Ronnie Upchurch
MP- 1 Installed a cover on the touch screen control.
MP- 10 The nut press wasn’t working. The nuts weren’t sliding down the left side track; cleaned it – working now.
MP- 24 Replaced a broken roller on the operator side gate.
I didn’t see the pump for 21 yet. If it comes in tomorrow we’ll have plenty of time to install it since molding is down for two days.
Later………………………………
Wednesday, March 16, 2011
Update 03-16-11
Hey Guys,
I just ordered a new Star Sprue Picker for MP26. I also ordered a new 5/16” screen for the green small grinder on MP22 (GR21). It has 3/16” screen and is grinding Santoprene and getting clogged up frequently.
I finally convinced Ken that we need to order 2 of the Special AEC grinders that I had spec’ed out to especially grind warm rubbery materials. He is turning in a CER for it today.
The pump for MP21 is due back in by the end of day today. Mark is out today and I have to leave at noon, so I told Ronnie just to prep it for tomorrow.
Thanks and keep up the hard work.
Joshua Ledbetter
Molding Maintenance Manager &
Manufacturing Engineer
Oreck Manufacturing Company
(C) 931-239-3235
(F) 931-646-7615
Ronnie Upchurch
MP-6 Adjusted the gate cutters; one side wasn’t cutting close enough.
MP-7 The portable hopper loader motor burned out. Replaced.
GR-4 I flipped the stationary blades & removed the rotating blades; no more blades in MRO. Also one of the adjustment set screws is missing from the front
stationary blade ; it’s metric.
I vacuumed out the oil pans on MP-6 -7 & 8
Tuesday, March 15, 2011
3-14-11 Mike Daniels
Worked on PMs
Made a core plug for mold in mp5
Swept shop
Mike Daniels
Technical Specialist
Oreck Manufacturing
Cell 931.287.6252
Eat. Sleep. Fish.
Monday, March 14, 2011
3.13.11 - Sean D-shift
It occurs about once every half hour, and always at the same place in the cycle, right before it starts to open and cores are pulling. I added some time before opening to it and it seemed to help.
Mp#14- The machine would shoot parts and then stop before building a shot again. Then the clamp would not open up in manual. Checked many switches, etc. Finally found the mold touch switch (LS2) was flickering. I re-adjusted it and checked operation, no further problems.
Continued with PM's..
Sean
Sunday, March 13, 2011
Ronnie Upchurch
MP-2 Cores not working – The hydraulics were hooked to core 1 & the switches were hooked to core 2. I moved the plug to # 1 side. It still wasn’t shifting.
I found one of the male quick connects was bad.
I emptied all the Nissei over flow jugs & the oil vac.
I moved the grinder from MP-12 to the shop. I cleaned it out. We need to order new blades for it.
MP-1 I changed out the grease tube on the lube system.
They brought 3 scales to the shop for repair. I cleaned them up & adjusted the level. 2 of them work fine, the other one I’ll take to Craig to check out. It
wouldn’t hold the zero or the tare setting.